Installing PrimeLine™
Check Valves
The following are general instructions for all
ASI check
valves.
Inlet Check Valve
-
Disconnect solvent intake line and remove inlet
valve.
-
Install inlet cartridge and housing with the
arrow on the cartridge pointing up, in the flow direction.
-
Firmly tighten housing and reconnect inlet fitting.
-
-
Important: It is absolutely essential
to use solvent inlet filters with at least a 10 micron rating or
finer. Failure to use an inlet filter will seriously compromise
the valve reliability.
Outlet Check Valve
- Disconnect the solvent outlet line and remove the old check
valve.
- Install outlet cartridge and housing with the arrow on the cartridge
pointing up.
- Firmly tighten housing and reconnect outlet fitting.
Priming the Pump
- Open the purge valve in order to eliminate any pressure
in the pump head. If there is no purge valve, then loosen the fittings
at the outlet check valve.
- Operate the pump at 4.0 mL or higher (the higher the flow rate
the faster the pump will prime).
- The pump should now draw solvent and prime without further operator
assistance. When no more air is seen venting from the outlet fittings
or purge waste outlet, tighten the outlet fittings and close the
purge valve.
Note: Running the seals dry while priming
the pump will not cause damage to the seals.
ASI
piston seals are made from UHMW-PE or Teflon blends that are
self-lubricating materials. However, filling the intake lines with as
much solvent as possible prior to priming will save time.
|